中(zhong)(zhong)證網(wang)訊(xun) 粵水(shui)電(002060)3月(yue)16日晚間發布公(gong)(gong)告(gao),2017年(nian)3月(yue)16日,公(gong)(gong)司收(shou)到廣州公(gong)(gong)共(gong)資源交(jiao)易中(zhong)(zhong)心發來的《中(zhong)(zhong)標(biao)(biao)(biao)通知(zhi)(zhi)書》,該《中(zhong)(zhong)標(biao)(biao)(biao)通知(zhi)(zhi)書》確定公(gong)(gong)司為(wei)“引韓(han)濟饒供水(shui)工程土建(jian)及安裝(zhuang)施工”的中(zhong)(zhong)標(biao)(biao)(biao)單位,中(zhong)(zhong)標(biao)(biao)(biao)下(xia)浮率為(wei)0.16%。根據招(zhao)標(biao)(biao)(biao)文件,該工程主(zhu)要建(jian)設內容(rong)包括新建(jian)泵站(zhan)2座,取、輸水(shui)管(guan)(guan)線總長36.769公(gong)(gong)里(li);其中(zhong)(zhong)主(zhu)管(guan)(guan)線長24.958公(gong)(gong)里(li),支(zhi)線長11.811公(gong)(gong)里(li);意(yi)溪抽水(shui)泵站(zhan)4用(yong)1備,總裝(zhuang)機(ji)容(rong)量為(wei)2000KW(4×500KW);黃岡河備用(yong)泵站(zhan)2臺,總裝(zhuang)機(ji)容(rong)量為(wei)1000KW(2×500KW)。工程施工中(zhong)(zhong)標(biao)(biao)(biao)金額(e)為(wei)71,072.27萬(wan)元(yuan),計劃(hua)工期約(yue)42個月(yue)。(陸泓)